Project Description

Issues arose where the main contractor commenced a series of adjudications whenever it considered its interim applications for time and money had been undervalued. The services provided included carrying out a delay analysis on the part of the Employer and adjudicating same when a difference concerning the quantification of the contactor’s interim entitlement to an extension of time became crystallised. This resolved the issue of repeated adjudications by the contractor.